InAfrika / Opinion / Investment analysis
From power plants to mines, seven cases show how loan terms, permits and government promises can shape the public cost of a deal for years.
Header photo: Wind turbines in northern Uruguay. Mx. Granger / Wikimedia Commons, CC0.
In 2015, during an electricity crisis, Ghana agreed to bring in two gas-fired power plants. Three years later, it ended the agreement. In 2021, an arbitration panel ruled that Ghana had ended it wrongfully and ordered the government to pay about US$134.35 million, plus interest, an extra charge that builds up while payment is outstanding, and separate legal costs. Arbitration is a way of resolving a dispute through independent decision-makers. Their written ruling is called an award. Part of the amount came from an early termination payment, a charge that can become due when an agreement ends before the agreed date. The panel used a formula that looked at what the plants could have generated over a period of up to 24 months. [1]
The dispute then moved to a US court. In September 2024, it entered a judgment, a formal court order, for about US$113.53 million plus further interest. The following year, the company confirmed in a court filing that Ghana had fulfilled its financial obligations under a settlement, an agreement between the parties to resolve the dispute. That filing gives the amount of the US judgment and leaves the final settlement price undisclosed. A sum requested, a sum ordered and a sum actually paid tell three different stories. [2]
Ghana’s case raises a question that belongs at the first meeting about any deal. What will it cost to stop? During an electricity shortage, the priority is getting power onto the grid. A few years later, demand, prices and the supply of power may all look different. At signing, officials should be able to see the price of ending the agreement under several scenarios. A government that waits until it wants to leave has already lost much of its bargaining power.
Mozambique shows what can happen when the public cannot see the obligations the state has taken on. Companies raised money for maritime security, a tuna fleet and shipyard services. The loans had government guarantees, promises that the state would repay lenders if the borrowers failed to do so. In 2016, Mozambique acknowledged to the International Monetary Fund that more than US$1 billion in government-guaranteed borrowing from abroad had previously gone undisclosed to the Fund. An English court later found that bribes had been paid in connection with the deals. A December 2024 order required Privinvest companies to pay Mozambique about US$534 million plus about US$40 million in interest and cover certain other losses. Those are amounts the court ordered, and the order provides no evidence of how much Mozambique collected. [3–5]
The weakness in that arrangement was easy to miss on a project brochure. A state guarantee gives the lender another source of repayment. It says little about whether a fishing fleet will catch enough fish, whether a shipyard will win enough business or whether buyers will pay on time. That is why independent checks on demand and costs matter before a guarantee is signed, alongside a public record showing how much the state could owe and when.
In Pakistan, the dispute at Reko Diq began after a mining licence was refused in 2011. An international panel awarded Tethyan Copper Company about US$5.9 billion in 2019. The parties later resolved the award in a deal that reorganised the project and allowed Antofagasta, one of the investors, to sell its interest. Antofagasta reported receiving US$945 million in the first half of 2023, including interest on the sale proceeds. That was the amount the company received for its exit under the new arrangement. The project still faced the practical challenge of getting built. In April 2026, Barrick said it would slow development and review the project until mid-2027 as security risks increased. [6–8]
Permits can be just as decisive as financing. In Mexico, US company Metalclad built a hazardous-waste facility that never opened. A municipal permit dispute and a state ecological decree formed part of a case under the North American Free Trade Agreement. An arbitration panel first awarded about US$16.69 million. A Canadian court overturned parts of the ruling while leaving a finding tied to the ecological decree in place. Metalclad later reported settling its claims against Mexico for US$16 million. Before spending on construction, everyone involved should know which authority issues each approval, when it can be challenged and what happens to the investment if the project cannot open. [9–10]
Germany illustrates a different kind of cost. After the 2011 Fukushima disaster, Germany brought forward the closure of its nuclear plants. The government agreed in 2021 to compensate utilities approximately €2.428 billion for electricity they could no longer generate and for certain investments affected by the decision. Vattenfall’s international arbitration ended that year. A government may have sound reasons to change policy. The budget still needs to reflect the cost of ending or changing rights granted under the earlier rules. [11–12]
Deals can also show what financial discipline makes possible. Uruguay used competitive bidding for wind power, asking developers to compete for contracts to sell electricity to the national utility. Under one programme, selected producers could secure purchase agreements of up to 20 years and had to pay to connect their projects to the grid. The long agreements gave developers a clearer view of future sales. The rules identified who would pay for the connection. In 2024, Uruguay generated 99% of its electricity from renewable sources, including hydropower, wind, biomass and solar. The national result reflects several sources of power and years of investment. [13–14]
Vietnam offers a different measure of success. The OECD reported that Samsung employed about 112,000 workers in the country in 2023. The investment built a large manufacturing base and helped Vietnam sell more goods overseas. The benefits to locally owned suppliers took longer to develop. In 2017, Samsung had 25 Vietnamese companies supplying it directly, but the OECD found that they provided areas such as packaging and services, with none making components for the finished products at that time. Counting jobs shows one gain. Tracking what local firms learn to make, and what they can sell to other customers later, shows another. [15]
The same discipline applies to a smaller business taking out a loan. Imagine a Tanzanian company that owes US$2 million a year in debt service, the total of the interest and loan repayments due that year. At an assumed exchange rate of 2,500 shillings to buy one US dollar, it needs TZS 5 billion to pay. At TZS 3,000 per dollar, it needs TZS 6 billion for the same bill. If the company has TZS 6.5 billion left from sales after paying running costs, its cushion after the loan payment shrinks from TZS 1.5 billion to TZS 500 million. One change in the exchange rate can absorb TZS 1 billion without the company borrowing another dollar.
A guarantee deserves the same calculation. Imagine a road that collects TZS 3 billion from drivers in a year. If the contract promises to bring the operator’s income up to TZS 5 billion, the state could owe TZS 2 billion if the guarantee applies in full. Before agreeing to it, officials need to know how often that gap could appear, whether payments have a ceiling and which part of the public budget would cover them. The same care belongs in agreements over land access, water use, compensation for affected households and cleanup when a project closes. [16]
Before the signatures, someone should be able to explain the entire agreement in ordinary language. What has to happen before money is released? Who checks the work before the next payment? Who can change the deal, and who pays if it must end? Then come the harder questions. Can the business make its payments if sales disappoint? Can the government afford its promises in a bad year? And what will workers, suppliers and communities still have after the investor has earned its return? The answers belong in the contract, in the budget and in the records used to track what the project actually delivers.